First Pfeiffer raw mill for Uzbekistan

The Turkish company DAL Teknik Makina, which is involved in turnkey projects worldwide, placed an order for a Pfeiffer MPS 3350 B vertical roller mill for raw meal which is to be used for the manufacture of grey cement and white cement. The grinding plant is scheduled to go on stream in Uzbekistan as early as next year.

The mill is guaranteed to achieve a raw meal capacity of 200 t/h for the production of grey cement. When it comes to white cement, the mill will be capable of processing 160 t/h of raw material. The installed ­power of the mill will be 1700 kW.

www.gpse.de

x

Related articles:

Issue 6/2017 GEBR. PFEIFFER SE

DAL Teknik Makina orders second Pfeiffer mill for Uzbekistan

In April 2017, DAL Teknik Makina, headquartered in Istanbul, ordered its second Pfeiffer mill for Uzbekistan. The first order, placed in 2013 for an MPS mill, and the resultant excellent relationship...

more
Issue 03/2011

Largest MPS vertical roller mill for India

Manikgarh Cement (A Division of Century Textile & Inds. Ltd.) ordered an MPS 6000 B raw mill and an MPS 3350 BK coal mill. The company belonging to the B.K. Birla Group of Companies, which is...

more
Issue 7/8/2011

Raw meal grinding in Northern Iraq

In January 2011, Sinoma (Suzhou) Construction Co. Ltd. acting as General Contractor placed a repeat order for an MPS 5000 B vertical roller mill for raw material grinding. The grinding plant designed...

more
Issue 04/2011

Raw meal grinding at the Izmir works

BATIÇIM Bat? Anadolu Çimento Sanayi A.S¸./Turkey placed an order for the supply of a Pfeiffer MPS roller mill which will increase the capacity of the cement works located in the east of Izmir’s...

more
Issue 1-2/2017 GEBR. PFEIFFER SE

Pfeiffer mill for HeidelbergCement’s Kaspi plant in Georgia

In November 2016, Gebr. Pfeiffer SE ­received an order to supply a vertical roller mill, which will be set up in the new 3000-t/d kiln line at Heidelberg­Cement Group’s Kaspi plant. The mill of the...

more