A TEC supplies calciner upgrade
At the top of the calcining system an A TEC Post Combustion Chamber (PCC) for optimized gas mixing and retention time increase will be installed. At the existing main burner, RDF (main burner quality), coal and animal meal as well as natural gas (only for start-up) will be used. On calciner side there are three fuel input positions – one of them the main fuel input from top into the hot gas chamber (HGC). The intake for shredded tires will be unchanged, but the existing calciner burner will be moved. The tertiary air distribution and the oxygen control are done by several dampers.