SUTCO UK LTD

SRF-manufacturing facility in Rugby now in full operation

In partnership with Cemex, a leading cement producer, Sita UK have committed themselves to develop two new waste treatment facilities with the aim of transforming commercial waste from across Birmingham into a high quality solid recovered fuel (SRF). The residual waste material arriving at the site is primarily collected from commercial and industrial businesses across the region and would otherwise go to landfill. The product known as Climafuel will be an alternative to coal, used at the Cemex cement works in Rugby, thus saving landfill space and contributing substantially to the reduction of the use of fossil fuel in this energy intensive process. Cemex is currently permitted to utilise up to 65 % of its fuel needs with this fuel.

After having produced this fuel very successfully at the first SRF plant at Landor Street in Birmingham for the last couple of years, Sita UK commissioned Sutco UK, the builder of the first SRF facility, as main contractor under competitive tender to design and build a second SRF facility in Rugby. This new £ 7 million facility includes several upgrades implementing the latest technology and will substantially increase Sita’s production capacity, then totaling around 250 000 t of Climafuel a year ­between the two facilities.

Hybrid design

The key aim of the design was to provide Sita with a facility capable of meeting the stringent fuel specification of the cement kiln industry, which requires the fuel to have a maximum moisture content of 15 %, a minimum calorific value of 17 MJ/kg, and a maximum chlorine content of 0.8 %. Sita also strived to extract valuable recyclables, targeting predominantly ferrous and non-ferrous metals, but also paper and dense plastics at times when the fuel product allows the extraction of these materials.

Sutco UK designed and built a hybrid solid recovered fuel facility, treating a mix of up to 240 000 t/a of commercial and industrial (C&I) waste and municipal solid waste (MSW). By means of proven mechanical and optical separation the facility combines the recovery of a high quality SRF along with the recovery of metals, paper and dense plastics. The heart of the process are four NIR units operating in two parallel lines, which first hit on paper, and then hit positively on SRF material. This concept ensures keeping the moisture content of the fuel low and prevents any contraries, such as PVC and stainless steel, from entering the fuel. The added bonus of the plant is that the two first NIRs may target dense plastics instead of paper at times when the CV of the fuel spec is high and the moisture content low. The target material of the NIRs is controlled automatically by the fuel analyser, thus ensuring not only that the fuel, which has a confetti-like consistency, has the precise chemical composition and calorific value required by Cemex, but also allowing recovery the best possible product outputs for the operator at all times.

Successful partnership

The contract was awarded in March 2014 with the mechanical installation starting in September 2014. Mechanical completion was achieved in December 2014 and the plant started trial operation in January 2015 with full operation taking place from April 2015. After a series of tests the plant has now been fully taken over by the client.

The Climafuel produced is a registered trade mark and is only used to describe this alternative fuel used by Cemex in the UK.

Sita UK Head of Alternative Fuels, Andy Hill, said: “The residual waste material that will be delivered to this facility would have gone to landfill but, instead, we are going to take out anything which can be recycled and then turn what’s left into a replacement fossil fuel – made to the exacting standards expected by our partners at Cemex.

We have been producing this fuel very successfully at our sister plant at Landor Street in Birmingham for the last couple of years, but this new facility implements the latest technology and will substantially increase our production capacity”.

This advanced SRF facility produces a more sustainable fuel to burn in cement kilns, reducing their reliance on fossil fuels while providing a long-term solution for the local community by diverting waste that cannot be recycled away from landfill.

//www.sutco-uk.com" target="_blank" >www.sutco-uk.com:www.sutco-uk.com

x

Related articles:

Issue 3/2023 LINDNER-RECYCLINGTECH GMBH

Cemex and Regenera Mexico trust in Lindner’s shredding experience for RDF production

In Mexico, waste, including industrial waste, is still frequently disposed of in landfill sites. Regenera, a Cemex subsidiary, focuses on developing circular economy solutions for the waste industry....

more
Issue 3/2021 CEMEX S.A.B. DE C.V.

Cemex invests US$ 25 million to phase out fossil fuels at Rugby cement plant in the UK

Cemex has announced that it is investing US$ 25 million in a new system to replace fossil fuels at its Rugby cement plant in the United Kingdom, as part of its “Future in Action” program to achieve...

more
Issue 5/2018 LINDNER-RECYCLINGTECH GMBH

SRF production facility saves one million tons of CO2

The Thermoteam Retznei site

ThermoTeam Alternativbrennstoffverwertungs GmbH in Feldkirchen near Graz/Austria is a joint venture between Lafarge Perlmooser Holding AG and Saubermacher Dienstleistungs AG. On 28.02.2018 the company...

more
Issue 5/2014 TEWS EQUIPMENT SYSTEMS

Starter kit for using solid recovered fuel in cement plants

In 1995, the equipment supplier Tews based in Büren/Germany tested its first system for the use of solid alternative fuels at the Kollenbach cement plant/Beckum operated by the present-day CEMEX....

more
Issue 5/2023 CEMEX S.A.B. DE C.V.

Cemex’s waste management business, Regenera, continues to grow

Cemex’s circular waste management business, Regenera, is expanding its operations in Mexico with the opening of a new facility in partnership with leading waste collection company PASA. The...

more