Special AFR

Proven experience with alternative fuels in the cement kiln process

In times of increasing energy costs, it is of vital interest for any company to save energy. To cut the energy costs for clinker production, the German cement industry started substitution of primary fuels with Alternative Fuels (AF) such as used oil or tyres after the first oil crisis of 1973. Today, alternative fuels and raw materials (AFR) include a wide range of types of hazardous and non-hazardous waste, as well as solid and liquid, organic and mineral waste.

1 Introduction

To cut the energy cost for clinker production, the German cement industry started substitution of primary fuels with Alternative Fuels (AF) such as used oil or tyres after the first oil shock in the early 1970s. Today, at more than 2 €/GJ energy costs and after establishing a reliable disposal management, alternative fuels and raw materials (AFR) include a wide range of types of hazardous and non-hazardous waste, as well as solid and liquid, organic and mineral waste, which have to be pre-processed, quality-monitored and tailor-made for existing kilns or newly-installed kilns and...

Related articles:

Issue 06/2014 KHD Humboldt Wedag GmbH

Alternative fuels in the cement manufacturing process

Due to the numerous possible sources of alternative fuels, the degree of variability in energy content, ash, moisture, particle size, form, density...

more
Issue 06/2014 FLSMIDTH

HOTDISCTM – a perfect combustion device for coarser alternative fuels

The substitution of fossil fuels in cement production has increased significantly in the last decade. Due to rising energy costs and ever stricter energy and environmental regulations, alternative fuels technology is becoming an important factor in controlling costs. To gain competitive edge, many cement and ...

more
Issue 06/2014 thyssenkrupp industrial solutions

PREPOL Step Combustor (SC) – a simple combustion system for solid alternative fuels

Operational experience shows that waste has to be pre-processed in a mechanical plant before its derived fuel can be used in a cement plant with standard equipment. The fuel must be comminuted to 20-50 mm to entrain into the gas stream and totally burnout within the short retention time in the calciner or at the kiln end. Alternatively, solid waste derived fuel ...

more
Issue 11/2012

KHD combustion chamber – flexible use of alternative fuels in the cement plant

Modern combustion technology permits extremely flexible reaction to the varying properties of alternative fuels.

more