MALAYSIA

Follow-up order for GPSE from YTL

The Chinese General Contractor TCDRI awarded Gebr. Pfeiffer SE a contract for a coal mill of the type MPS 2800 BK. With this mill, the cement producer YTL will install the third coal mill of this series in one of his ­cement works in Malaysia.

Featuring an installed power of 700 kW, the coal mill will be grinding 35 t/h of a sub-bituminous coal with a total moisture content of 25 % to a product fineness of ≤ 10 % R 90 µm.

The delivery of the mill is scheduled for the end of 2014.

//www.gpse.de" target="_blank" >www.gpse.de:www.gpse.de

Related articles:

Issue 03/2014

MPS mills for coal grinding

1 Introduction Two mill systems are employed for most coal grinding applications in the cement industry. These are, on the one hand, vertical roller...

more
Issue 10/2012

New vertical roller mills for Malaysia

In March 2012, KHD Humboldt Wedag International AG, acting as General Contractor, was able to secure an order from Straits Cement, a subsidiary of...

more