Modernization at Aalborg Portland A/S

Aalborg Portland A/S of Denmark placed an order with Christian Pfeiffer to upgrade cement mill No. 2 in July 2011. Based in the North of Denmark and part of the Italian Cementir Holding, the company Aalborg Portland A/S is investing in the modernisation of its already existing cement mill which produces high-quality white cement. Besides a distinct improvement in product quality, the main reasons for this decision are to enhance manufacturing efficiency and improve the energy efficiency of the plant.

The scope of the order placed with CPB includes the engineering, the supply of plant and materials handling technology including steel construction, surveillance of the installation work and commissioning of the plant. The core of the plant consists of the high-performance separator QDK107-Z from the latest generation of separators and a process filter for fines separation. Thanks to this concept, it is possible to cool the cement down to a maximum temperature of 70° C as requested by the customer.

Special requirements are placed on the engineering due to the limited space available.

The delivery of the machines is planned for December 2011; the beginning of installation work is scheduled to start on 2nd January 2012. Operational production is expected to start at the beginning of April after the plant has been commissioned.

www.christianpfeiffer.net

x

Related articles:

Issue 3/2019 CHRISTIAN PFEIFFER MASCHINENFABRIK GMBH

New cement plant from Christian Pfeiffer for YD Madencilik A.S. in Turkey

Christian Pfeiffer will supply two grinding plants for a new cement plant of the YD Madencilik A.S. (Üstyapi Insaat Group). In the Düzce region, 200 km east of Istanbul, a new cement plant of the YD...

more
Issue 4/2017 A TEC PRODUCTION & SERVICE GMBH

Two new A TEC calciners for Aalborg Portland Cement

Aalborg Portland Cementir Holding has awarded A TEC the contract for upgrading Cement Kiln 87 in Aalborg/Denmark. It is a 4500 t/d semi-dry kiln system which was commissioned in 1988. Two new...

more

Mill and classifier operation: The Pfeiffer Seminar 2010

Following the very successful realization of our last process-technological training courses in the past, customers are welcome to participate in our next three days intensive training held at...

more
Issue 12/2011

Positive operating experience after separator replacement

In July 2010, Phoenix Zement in Beckum optimized a grinding plant by changing the separator (see report in ZKG INTERNATIONAL 09/2010, pp. 20-23). The background to this investment by Phoenix was the...

more
Issue 09/2014 MALAYSIA

Christian Pfeiffer receives large order for Kuching

In spring 2014, Christian Pfeiffer received the order to erect a turnkey cement grinding plant including silos and packing facility for Caha Mata Sarawak (CMS) in Kuching/Malaysia. The order at a...

more