First fully decarbonised cement plant in Germany

Heidelberg Materials’ cement plant in Geseke, Germany
Copyright: Steffen Höft for Heidelberg Materials
Heidelberg Materials’ cement plant in Geseke, Germany
Copyright: Steffen Höft for Heidelberg Materials
EU Innovation Fund backs Heidelberg Materials' GeZero project with €191 million

The EU Innovation Fund, one of the world’s largest funding programmes for innovative low-carbon technologies, will support Heidelberg Materials with €191 million to develop a unique CCS value chain at the German Geseke cement plant. The funding complements substantial investments by the company. Following the successful conclusion of the Grant Agreement, the project will officially be launched on 1 January 2024. Geseke is set to become the first German cement plant that will produce carbon captured net-zero cement and clinker.

“The successful Grant Agreement demonstrates the relevance of GeZero for the decarbonisation of our sector, and the trust that European authorities place in our approach,” says Dr Nicola Kimm, Chief Sustainability Officer and Member of the Managing Board of Heidelberg Materials. “We just recently introduced our evoZero brand, the world's first carbon captured net-zero cement on the market. The product will initially be offered through our Brevik CCS project in Norway. Once other capture projects such as GeZero start operations, these plants will also be able to deliver net-zero cement and clinker to customers, significantly speeding up the decarbonisation of our industry.”

Mona Neubaur, Minister for Economic Affairs, Industry, Climate Action and Energy and Deputy Prime Minister of the State of North Rhine-Westphalia: “About one third of the German cement production is located in North Rhine-Westphalia. We are therefore delighted that the first carbon-free cement plant in Geseke in the district of Soest is a flagship project for a sustainable and climate-neutral future in the cement industry. GeZero shows how climate protection through new technologies and processes can also be achieved in energy-intensive industries. The project represents a decisive step towards a future-proof cement production and the transition to a net-zero industry in North Rhine-Westphalia, Germany and beyond.”

3D visualisation of the completed GeZero installation at the Geseke plant
Copyright: Heidelberg Materials

3D visualisation of the completed GeZero installation at the Geseke plant
Copyright: Heidelberg Materials
In addition to the construction of the capture facility and a new oxyfuel kiln, GeZero’s unique approach includes a CO₂ transport solution via train to bridge the gap until the necessary pipeline infrastructure will be available and is scaled to capture around 700000 tonnes of CO₂ annually. The CO₂ will be transported to Wintershall Dea’s CO₂ hub to be safely stored in the North Sea. Construction of the facility will start in 2026, and commissioning is planned for 2029.

The EU Innovation Fund focuses on flagship projects with European value added that can bring significant emission reductions. In response to its third call for large-scale projects, the European Commission had received 239 applications. 37 were selected for funding and have signed the Grant Agreement. Heidelberg Materials’ ANRAV projects in Bulgaria received backing by the EU Innovation Fund already last year. The project aims to establish the first full-chain CCUS facility in Eastern Europe, with a capture capacity of about 800000 t CO₂ per year starting from 2028.

www.heidelbergmaterials.com

Related articles:

Issue 6/2023 HEIDELBERG MATERIALS

CCS project: Heidelberg Materials gets support from the EU Innovation Fund

The EU Innovation Fund, one of the world’s largest funding programmes for innovative low-carbon technologies, has selected Heidelberg Materials’ pioneering GeZero Carbon Capture and Storage (CCS)...

more
Issue 5/2022 HEIDELBERGCEMENT AG

Pioneering CCUS in Bulgaria: HeidelbergCement’s ANRAV project selected by EU Innovation Fund

HeidelbergCement’s newly launched ANRAV CCUS project has been selected for Grant Agreement Preparation by the EU Innovation Fund, meaning that the project’s implementation will be supported. ANRAV...

more
Issue 8/2023 HEIDELBERG MATERIALS

Major step towards full-scale CCUS in Eastern Europe: Heidelberg Materials starts carbon capture pilot in Bulgaria

In the presence of Milena Stoycheva, Bulgaria’s Minister of Innovation and Growth, and representatives of Heidelberg Materials and the local community, the start of construction for the pilot carbon...

more
Issue 07/2024 LHOIST

“EVEREST”: EU supports innovative decarbonisation of the lime industry

Europe’s largest limestone plant, the Flandersbach plant of Lhoist Germany Rheinkalk GmbH in Wülfrath, is preselected to receive funding in the amount of millions from the EU Innovation Fund. Unique...

more
Issue 05/2024 HEIDELBERG MATERIALS | LINDE

Groundbreaking ceremony for the world’s first large-scale carbon capture and utilisation facility in the cement industry

On 19 June 2024, Linde and Heidelberg Materials hosted a groundbreaking ceremony for their large-scale carbon capture and liquefaction plant in Lengfurt/Germany. Christian Knell, General Manager of...

more