Bedeschi long belt conveyor erection for LafargeHolcim Maroc
Erection works are well under way at the LafargeHolcim Maroc project site in Souss/Morocco. Following an intense civil work phase, during which the single trusses were preassembled and equipped with the mechanical comports, the 4.3 km long distance belt conveyor starts taking shape. The site team is taking full advantage of Trimble Connect to facilitate the erection works. Bedeschi designs, executes and delivers every component of this outstanding turn-key project.
Hard environments, high slopes and difficult accesses are not impossible, if overtaken by the implementation of smart solutions.
The conveyor, which trusses up to 5 t completely assembled at ground, has been erected on the mountain using a suspended cableway. The system, installed and operated by the Bedeschi team with the partner SEIK, allowed fast-track operations with a high degree of Safety and Quality.
This advanced methodology allowed Bedeschi to carry out the erection within a tight schedule and limited impact on the local environment to the full satisfaction of the final client.
Bedeschi confirmed its reliability as EPC Contractor for the material handling sector and continues to grow and expand its expertise by the usage of technologies and innovation.